News

RAK Central: Every Project in Ras Al Khaimah’s New Downtown and When It’s Due

RAK Central is Ras Al Khaimah's new business district, rising off the E11 opposite Al Hamra Golf Club. Here is every announced project, who is building it and when each one is due.

RAK Central

Updated 9 November 2026: RAK Central Square, the five-tower office campus at the heart of the district, has topped out, and 20% of its space is already leased. The project table, timeline and FAQs below are updated.

Drive the E11 past Al Hamra and you will notice cranes where there used to be sand. That is RAK Central, the business district Marjan is building as Ras Al Khaimah’s first proper downtown: Grade A offices, apartment towers, hotels, shops and parks on one masterplan, a short hop inland from Al Marjan Island.

Since Marjan unveiled the district in early 2024, the announcements have arrived one developer at a time, and we have covered them as they landed. This page pulls them together: what RAK Central is, who is building what, where each project stands and what it means if you live, buy or do business in RAK. Every date below is the one the developer has announced, not a guarantee, and we review this page as milestones land.

RAK Central at a glance

At a glance
Master developer
Marjan, which merged with RAK Hospitality Holding in October 2025
Location
Sheikh Mohammed bin Salem Al Qasimi Street, directly off the E11, overlooking Al Hamra Golf Club
Size
8.37 million sq ft of gross floor area, per Marjan
The plan
About 3 million sq ft of rentable offices, more than 7,000 apartments, over 1,000 hotel keys, retail, parks, public spaces and a central town square
Plots
All 26 development plots sold, according to Marjan (November 2026)
Infrastructure
Roads, utilities, cycle tracks and landscaping completed September 2025
Latest milestone
RAK Central Square topped out in November 2026
Full build-out
Announced for 2030, delivered in phases

Figures from Marjan announcements, January 2024 to November 2026. The apartment target has grown from more than 4,000 at launch to more than 7,000.

Where is RAK Central?

Not on Al Marjan Island, which is the most common mix-up. RAK Central sits on the mainland along Sheikh Mohammed bin Salem Al Qasimi Street, right off the E11 and facing Al Hamra Golf Club with the Gulf beyond. Marjan pitches it as the gateway to the emirate, with road links to RAK International Airport and Dubai. The island, with Wynn and the resort strip, is a short drive away, and our complete guide to Al Marjan Island covers that side of the story.

See RAK Central on Google Maps

WOW-RAK Expert Tip: RAK Central and Al Marjan Island are different products. RAK Central is a business district first, built around offices and year-round residents. The island is a resort and holiday-home market. Compare them on rental demand and who lives there, not just on price per square foot.

Every RAK Central project and where it stands

ProjectDeveloperWhat it isAnnounced forStatus
RAK Central SquareMarjan and RAKEZFive Grade A office buildingsOpening Q4 2027Topped out November 2026, facade and building services under way, 20% leased
One RAK CentralPantheon DevelopmentApartments, offices and hotel apartmentsCompletion Q4 2027Under construction since October 2025
JunaDara Properties27-storey tower, about 350 homesCompletion Q4 2027Land acquired April 2025
Colibri ViewsMajor Developments31-storey furnished apartmentsNo official date publishedLaunched October 2025, off-plan
Radisson Blu Hotel and ResidencesBNW Developments361-room hotel and 222 branded residencesOpening 2029Launched February 2026, off-plan

Status from the latest Marjan or developer update we could find. Reviewed 9 November 2026.

Marjan’s November 2026 statement also lists Lapis Properties and Sugee Properties among the developers committed to the district. We have not yet seen project details from either, and they will join the table when they announce.

RAK Central Square: The Office Campus

RAK Central

The anchor of the whole district is a five-building office campus, first announced as RAK Central HQ and now branded RAK Central Square. It is a joint venture between Marjan and RAK Economic Zone (RAKEZ), designed by Gensler, built by ALEC and targeting LEED Gold. Leasing is handled by JLL, which we covered when RAKEZ and Marjan appointed JLL to lease the building.

In early November 2026 Marjan and RAKEZ marked the topping out, the point where all five towers reach full height. According to Marjan, structural works are complete, facade installation and mechanical, electrical and plumbing works are under way and the site has logged more than five million working hours without a reportable safety incident. Opening is announced for Q4 2027. Khaleej Times, reporting from the ceremony, gave a September 2027 target, so read it as late 2027 and do not set your calendar by either.

The more interesting number is occupancy. RAKEZ Group CEO Ramy Jallad told Khaleej Times that 20% of the space is already leased, with Marjan, the RAK Tourism Development Authority and Al Hamra among the confirmed occupants and reservations in from multinational firms in the legal, entertainment and retail sectors. Offices will range from around 20 square metres to multiple floors, so this is not just a home for big headquarters.

For everyone else, the bit that matters is at ground level. The leasing brochure shows the five towers set on a podium around a pedestrianised town square, with more than 2,200 sq m earmarked for food and drink and more than 1,000 sq m for shops. No restaurant or cafe operators have been named yet.

RAK Central Square office towers under construction off the E11 in Ras Al Khaimah

One RAK Central by Pantheon Development

Dubai’s Pantheon Development was among the first private developers to commit, securing land in the masterplan before most of the market had heard of the place. Its first project, launched in late 2024 as One Central, packs 312 apartments, a Grade A office building and hotel apartments into roughly 450,000 sq ft, and was reported sold out on launch day.

Pantheon broke ground in October 2025 and has since described a wider AED 1.6 billion investment across six plots in RAK Central. Completion of the first phase is announced for Q4 2027.

Juna by Dara Properties

Dara Properties made its RAK debut here in April 2025 with a 50,000 sq ft plot for a 27-storey residential tower: about 350 homes from studios to three-bedroom apartments, with a pool, gym and padel courts. Marjan’s 2026 project list names it Juna. Completion is announced for Q4 2027. We have not yet seen a construction update or published pricing.

Colibri Views by Major Developments

The developer behind Manta Bay bought into RAK Central in July 2025, announcing a mixed-use scheme of offices, homes and retail. Its launch here, Colibri Views, followed in October 2025: 31 floors of fully furnished apartments, a rooftop football simulator designed with Patrice Evra, a sky observatory deck and a three-year post-handover payment plan.

The developer has not published an official handover date, so treat any date you see on a property portal with caution.

Radisson Blu Hotel and Residences

The first hotel brand confirmed for RAK Central is Radisson Blu, developed by BNW Developments with Radisson Hotel Group. The plan is a 361-room hotel with five restaurants and bars, a rooftop pool bar, spa and kids’ club, sitting above retail and a cinema, plus 222 Radisson Blu branded residences.

BNW launched sales in February 2026 and lists handover for Q4 2029. At the time of writing its project page shows residences from AED 1.12 million and hotel units from AED 1.35 million. BNW also opened its first sales gallery and experience centre in RAK in January 2026. Marjan’s plan calls for more hotels than this one, but no other operator has been named yet.

RAK Central masterplan in Ras Al Khaimah with offices, homes and hotels

Infrastructure: The Part That is Actually Finished

In September 2025 Marjan announced all infrastructure works complete: roads, cycle tracks, stormwater, sewerage, water, power, street lighting and landscaping. That matters more than it sounds. Serviced plots let private developers start building instead of waiting on the master developer, which is why several towers are now moving at the same time. Next in line is a district cooling plant, which Marjan says will chill more than 40 buildings across the masterplan.

What RAK Central means for you

If you live in RAK

Right now it is still a construction site, so there is nothing to visit. The topping out does mean the timeline is getting real: the offices, and the cafes and restaurants planned around the town square below them, are lined up for late 2027. Thousands of office workers arriving every day is what tends to pull in gyms, coffee and lunch spots, and Marjan’s plan also includes parks, retail and a university campus, though no university operator has been announced. Expect more traffic on the Al Hamra stretch of the E11 once the towers fill up.

If you are thinking of buying

Everything residential in RAK Central is off-plan. Ask for the project’s escrow account details, check the payment plan against the announced completion date and remember that dates here have already moved: the office complex went from Q4 2026 to Q4 2027. The office campus hitting its topping-out on schedule is a good sign for the district, but it says nothing about any individual tower. Plan for a delay rather than being surprised by one.

WOW-RAK Expert Tip: Property portals often quote RAK Central handover dates the developer itself has not published. If a date matters to your decision, ask the sales team to show it to you in the sale and purchase agreement, not the brochure.

If you run a business

RAK Central Square is billed as the emirate’s first Grade A commercial development, and with RAKEZ as a partner it is an obvious next step for free zone companies outgrowing a flexi desk. With a fifth of the space already spoken for a year out, and units starting from around 20 square metres, it is worth talking to JLL early if you want a particular floor or a town square view.

RAK Central timeline

At a glance
January 2024
Marjan launches RAK Central
Late 2024
Pantheon launches One Central; Marjan and RAKEZ announce the office campus
April 2025
Dara Properties buys its plot
June 2025
JLL appointed to lease the office campus
July 2025
Major Developments buys land
September 2025
Infrastructure complete; Marjan says every plot is sold
October 2025
Pantheon breaks ground; Colibri Views launches
January and February 2026
Radisson Blu signed and launched
May 2026
Office campus rebranded RAK Central Square, opening announced for Q4 2027
November 2026
RAK Central Square tops out with 20% of its space leased
Q4 2027
Office campus, One RAK Central and Juna announced for completion
2029
Radisson Blu announced to open
2030
Full build-out announced

Future dates are as announced by Marjan and the developers.

RAK Central FAQs

What is RAK Central?

RAK Central is Marjan’s new business district in Ras Al Khaimah, combining Grade A offices, apartment towers, hotels, retail and parks on one masterplan off the E11.

Is RAK Central on Al Marjan Island?

No. RAK Central is on the mainland along Sheikh Mohammed bin Salem Al Qasimi Street, overlooking Al Hamra Golf Club. Al Marjan Island is a short drive away.

When does RAK Central Square open?

Marjan has announced Q4 2027. The five office towers topped out in November 2026 and 20% of the space was leased by then, with Marjan, the RAK Tourism Development Authority and Al Hamra among the confirmed occupants.

When will RAK Central be finished?

It is being delivered in phases. The first office buildings are announced to open in Q4 2027 and Marjan has announced full build-out for 2030.

Who is building in RAK Central?

Marjan is the master developer. Announced projects include RAK Central Square by Marjan and RAKEZ, One RAK Central by Pantheon Development, Juna by Dara Properties, Colibri Views by Major Developments and the Radisson Blu Hotel and Residences by BNW Developments. Lapis Properties and Sugee Properties are also among the committed developers.

Can foreigners buy property in RAK Central?

Yes. Marjan markets RAK Central as a freehold district with 100% foreign ownership. As with any off-plan purchase, check the developer’s escrow arrangements before paying.

Is there a hotel in RAK Central?

Not yet. The first confirmed hotel is a 361-room Radisson Blu, announced to open in 2029, with more hotels planned in the masterplan.

We will keep adding to this page as each tower tops out and each new developer signs. Next up on the watch list: the first restaurant and cafe names for the town square, project details from Lapis and Sugee, and whether One RAK Central and Juna hold their Q4 2027 dates.

Last reviewed 9 November 2026.

Related questions

Abhishek Tiwari

I'm Abhishek Tiwari. I'm critical. I'm detail-oriented. I'm neat. I'm technical. I'm creative. I'm an out-of-the-box thinker. I'm dedicated. I'm emotional. I'm communicator. I'm crisp. I'm dramatic. I'm above the line. I'm below the line. I'm spender. I'm digital. I'm strategist. I'm revolutionary. I'm a marketer. Inside and out.

More stories by Abhishek